Western Colorado cities expect big savings from solar power

GRAND JUNCTION – Don’t let the chilly air and shorter days fool you: Hundreds of solar panels located off Interstate 70 near Palisade are working just fine.

Come January, the 12-acre solar garden will go online and fully offset electricity costs for Palisade, saving the town an estimated $1.2 million over the next 20 years.

The panels also will save the city of Grand Junction $600,000 over the next two decades. The 2-megawatt solar garden will create renewable energy to power 75 percent of the electricity needs at the Grand Junction police station and add to the city’s existing solar credit portfolio to completely power the water plant at 26¼ Road with renewable energy.

The cities of Rifle and Fruita, Mesa County Libraries, the Grand Junction Housing Authority, the Museums of Western Colorado and other subscribers also will benefit from the Grand Valley’s latest solar garden, thanks to Xcel Energy’s Solar Rewards Community Program.

The partnership with Denver-based solar garden developer Oak Leaf Energy Partners benefits Palisade even further. The company makes annual lease payments on the town’s land.

“There’s no investment on our part,” Palisade town treasurer Joe Vlach said. “It’s worth it.”

Mike McCabe, a partner with Oak Leaf Energy Partners, offered Grand Valley officials a tour of the solar farm on a recent afternoon.

He said the solar garden site in a low area near the new Cameo Shooting and Education Complex is situated in a good location being visible from the interstate but difficult to access and far away from residential development.

“It’s a natural fit,” he said. “It’s kind of located on an island.”

The Grand and San Luis valleys are considered the sunniest parts of the state and collect the most solar energy, he said.

The sun-tracking panels are easy to maintain and automatically shut down only in the event of wind blowing more than 40 mph.

The roughly $4 million project has been in the planning stages for about two years, but only took a few months to install, McCabe said.

Oak Leaf is seeking more sites to add the solar gardens after recently being approved by Xcel to add projects totaling 34 megawatts in 2-megawatt solar gardens, McCabe said.

Ron Quarles, community development director for the town of Palisade, tours a solar farm near Cameo that goes online in January.
Tags

PREV

PREVIOUS

Xcel Energy’s climate plan includes carbon capture

As Xcel Energy executives announced their vision of delivering zero-carbon electricity by 2050 in Denver, they may have also revived a long debate over the viability of carbon capture technology. Minneapolis-based Xcel  — Colorado’s largest power utility — in 2004 fought a 10 percent renewable energy mandate in Colorado. Now it says it sees a […]

NEXT

NEXT UP

In oversight role, DeGette, other House Democrats aim for both check and balance

WASHINGTON – Rep. Elijah E. Cummings has seen the headlines. The 12-term Maryland Democrat, who in January will take control of the House Oversight and Government Reform Committee, knows he has the power to become President Donald Trump’s worst nightmare. For now, he’s taking a more measured approach. “A nightmare has to be in the […]


Welcome Back.

Streak: 9 days i

Stories you've missed since your last login:

Stories you've saved for later:

Recommended stories based on your interests:

Edit my interests