Colorado Politics

Denver auditor finds oversight failures in $175.6M 16th Street project

Surprise historic sewer discovery delayed completion a year, cost $18M

The Denver Auditor recently found significant oversight and contracting problems with the $175.6 million 16th Street Improvement Project, including an $18 million contract increase and a nearly one-year extension that bypassed City Council review.

The report also found that inadequate planning for historic brick sewers contributed to the overruns, even after one of the three qualified contractors withdrew from bidding because of utility risks. The city proceeded without fully investigating those risks, which later contributed to the $18 million increase and nearly yearlong delay.

a brick tunnel, the historic sewer line found under Denver's 16th street during construction
A historic sewer line that was found under 16th Street during rennovations, causing a year delay and $18 million in cost overruns. (Courtesy photo, PCL Construction)

“Because the city did not consider the sewer while planning the 16th Street Improvement Project, businesses on 16th Street had construction lingering outside their doors for nearly a year longer than expected,” Auditor Timothy O’Brien said in a statement.

Denver City Council approved $149 million in 16th Street renovation costs in 2021 and the brick sewer was discovered the following year, which halted construction. PCL Construction was tabbed as the lead contractor.

A brick sewer is an underground drainage or wastewater conduit built with specialized bricks, commonly dating back to the early 19th and 20th centuries. Officials do not know the location of every brick sewer in Denver.

Brick sewers typically sit beneath streets and other infrastructure, limiting access. Their age, deterioration and irregular shapes can complicate repairs and upgrades.

Denver’s Department of Transportation & Infrastructure agreed with most, but not all of the auditor’s 10 recommendations.

Officials even let PCL slide on more than $1,000,000 in fines.

“Contract terms were not always followed,” according to the news release. “Department leaders said they waived damages for missed completion due dates to support the city’s relationship with PCL. This meant the city did not collect $1.03 million in damages for delays.”

DOTI “disagreed with our recommendation to strengthen its documentation ability to trace quality oversight processes and ensure contract compliance.”

Among the audit findings:

  • DOTI did not ensure a transparent competitive bidding process.
  • DOTI provided little oversight of PCL’s subcontractors because it assumed the lump-sum contract prevented the city from reviewing subcontracting records, leaving the department with little documentation to verify how subcontractors were selected and managed.
  • The contract terms were not always followed.

With a “construction-focused scope,” the audit did not include a review of the economic impact on businesses along 16th Street.

DOTI agreed with the following recommendations and has since implemented them: Update general contract guidance; Use a formal project delivery selection methodology; Strengthen the department’s internally developed project delivery selection methodology

The $175 million project overhauling Denver’s main corridor wrapped in October, with the official reopening exactly 43 years after its inaugural in 1982. The project, which began in 2022 and was expected to be completed by late 2024, was to address the deteriorating infrastructure, particularly drainage problems.

More than 200 trees were planted to provide a larger canopy for visitors to escape from the intense Colorado sun and included new art installations and children’s play areas.

Denver Gazette reporters Bernadette Berdychowski and Stephen Barr contributed to this report.


PREV

PREVIOUS

US set for largest mass visa revocation in history targeting up to 200,000 foreigners, officials say

WASHINGTON (AP) — The Trump administration is preparing to revoke the business and tourism visas of up to 200,000 foreigners who have applied for or are currently seeking asylum status in the United States. If it happens, the move would be the largest single mass revocation of visas in U.S. history and would likely face […]

NEXT

NEXT UP

Federal judge hears arguments about Colorado's 3-day gun purchase waiting period

A federal judge heard arguments on Monday about the constitutionality of a 2023 Colorado law that generally imposes a three-day waiting period on firearm purchases after the initiation of a background check. The test that the U.S. Supreme Court created in 2022 for assessing firearm regulations’ compliance with the Second Amendment occurs in two phases. […]


Welcome Back.

Streak: 9 days i

Stories you've missed since your last login:

Stories you've saved for later:

Recommended stories based on your interests:

Edit my interests