Auditor: City let jail construction project go millions over budget, years behind schedule

The Denver Department of Transportation and Infrastructure allowed a jail construction project to go nearly $2 million over budget and three years past deadline, according to a report released by Auditor Timothy O’Brien Thursday.

The report examined the buildout contract for Denver County Jail Building 24, identifying numerous instances of additional work and costs which O’Brien said the department failed to adequately explain or document.

“Change orders after the fact, light documentation on a project, years of delays, and extra cost for work that may have been foreseeable – this doesn’t pass the test for public accountability and responsible management of public funds,” O’Brien said.

During construction, many subcontractors billed for more than they originally quoted for the work, adding nearly $2 million in costs, according to the report. Some of the subcontractors didn’t even have original price quotes on file.

In addition, due to substantial change orders during construction, the project was extended for an additional 1,001 days, when it was only scheduled to take 262 days in total. This years-long delay also increased construction costs.

Though the building was supposed to be finished by January 2018, it still was not complete at the time of the audit, the report said.

“Effective project management is essential to combat rising construction costs in the city,” O’Brien said. “Based on the management of this construction contract, city managers need to make sure they’re keeping a closer eye on the work being done to make sure the public is getting what they pay for.”

The report recommends the department improve how it monitors amounts billed by subcontractors, reconcile price quotes to the amounts invoiced, complete change orders in a timely manner and document the explanation of all increased costs.

The department has agreed to all recommendations and committed to implement them by Aug. 1.

FILE PHOTO
denverauditor.org
Tags denver

PREV

PREVIOUS

Mobile home company to pay $25,000, implement new security measures after data breach

A Colorado mobile home company has come to an agreement with the state’s attorney general’s office to pay $25,000 and implement new safety measures after a security breach released more than 15,000 people’s sensitive information. Over 700 Coloradans were affected in the breach that targeted Impact MHC’s email system beginning in October of 2018 and […]

NEXT

NEXT UP

City of Loveland hires outside firm to review police department practices

The City of Loveland has hired an outside law enforcement and public safety consulting firm to conduct reviews of its police department following the forceful arrest of an elderly woman in June 2020, according to a news release from the city Thursday afternoon. The Chicago-based Hillard Heintze will conduct a professional standards investigation related to […]


Welcome Back.

Streak: 9 days i

Stories you've missed since your last login:

Stories you've saved for later:

Recommended stories based on your interests:

Edit my interests